site logo

CANNITEC INTERNATIONAL CO. LTD V. SOLEL BONEH NIG. LTD (2017 (2017)

case summary

Supreme Court of Nigeria

Before Their Lordships:

  • O. Rhodes-Vivour JSC
  • Olukayode Ariwoola JSC
  • Clara Bata Ogunbiyi JSC
  • Chima Centus Nweze JSC
  • Amiru Sanusi JSC

Parties:

Appellant:

  • Cannitec International Company Ltd

Respondent:

  • Solel Boneh Nigeria Ltd
Suit number: SC. 88/2007

Background

This case involves a contractual dispute between Cannitec International Company Ltd (the Appellant) and Solel Boneh Nigeria Ltd (the Respondent) regarding the laying of terrazzo and skirting works at the University of Port Harcourt Teaching Hospital. The Appellant claimed the remaining balance of a contractual sum for subcontract work completed between 1999 and 2001, which included work on several blocks, particularly Block H and the Mortuary Block. The initial agreement set the rates for work at N1,400 per square meter for terrazzo and N300 per linear meter for skirting.

Issues

The central issue was whether a valid contract existed for the appellant to perform additional work at revised rates. Key aspects of this case include:

  1. Existence of a valid contract regarding the work in question.
  2. Whether any counter-offers from the Appellant were sufficient to alter the terms of the initial agreement.

Ratio Decidendi

The Supreme Court upheld the Court of Appeal's decision to dismiss the appeal, citing that:

  1. A valid contract requires clear offer and acceptance, along with mutual agreement on material points.
  2. The Appellant's counter-offer was effectively a rejection of the original terms, leading to a lack of agreement.
  3. The conduct and correspondence between parties did not establish a binding agreement.

Court Findings

The Supreme Court's findings highlighted that:

  1. Exhibit B, a letter from the Respondent, reiterated the original terms, to which the Appellant responded with a counter-offer that was not accepted.
  2. The submission of third-party documents claiming agreements that never involved the Respondent created no enforceable contract.
  3. The previous trial court's decision was overturned based on the evidence that showed no mutual agreement had been reached.

Conclusion

The Supreme Court concluded that there was no enforceable contract between the parties as the correspondence did not constitute a valid acceptance of terms. The dismissal of the appeal affirmed the Court of Appeal’s ruling, holding that the Appellant had no grounds for claiming the remaining balance.

Significance

This case is significant as it underscores the necessity for clarity and mutual agreement in contract law. It illustrates the importance of understanding how counter-offers impact existing agreements and the binding nature of written correspondence in establishing enforceable contracts.

Counsel:

  • S. Brisibe (with him, E.I. Erebi) - for the Appellant
  • Mrs. R. Chris Garuba (with her, R. Odo and A. Omah) - for the Respondent